MHN-complex
MNW-NF bride installation project was awarded to L&T as EPC contract. 133mtr 350 MT bridge was intended to connect the existing MNW process platform to existing NF (BHF) platform as after BHN disaster the connecting bridges was collapsed. The bridge is now very instrumental in connecting newly commissioned MNP and LQ platform with NA process come well head platform.
UPCEM Scope: UPCEM organized the HAZID work shop with L&T and Bureau Veritas for assessing the risk and SIMPOS. Later the course and detailed QRA report was reviewed and presented for client approval.