The Heera Redevelopment (HRD) process platform project in the Arabian Sea, at approximately 70 kilometers South-West of Mumbai, India.

UPCEM Scope: Complete Pre-Commissioning, Commissioning & Handover Management for complete project and Commissioning Manpower Supply.

Processing facilities at process platform consist of broadly the following: –

  • Well fluid receiving system
  • HP separators system
  • Process gas compressor
  • LP compression system
  • Gas knock out vessel
  • Condensate system
  • Flare system
  • Seawater lifting and filtration
  • Diesel fuel system
  • Emergency diesel generator
  • Main power generation system
  • Instrument air/Utility air system
  • Nitrogen system
  • Utility water system
  • Hypochlorite system
  • Sewage treatment system